Simplified Construction Estimate Max Fajardo.pdf — Working & Extended

The author simplifies the estimation of concrete hollow blocks (CHB) by providing standard ratios for mortar and the number of bags of cement required per square meter of wall. This section is particularly noted for its "rule of thumb" tables that expedite the estimation process for vertical structures.

5.0 x 3.0 = 15 sq. m.

: The book covers everything from earthwork (excavation and backfill) to finishing works (painting, tiling, and roofing). It provides detailed tables for concrete mixtures, masonry, and even electrical or plumbing estimates. Simplified Construction Estimate Max Fajardo.pdf