Tower Crane Dismantling Method Statement Better Direct
Tower Crane Dismantling Method Statement is a critical safety document that outlines the step-by-step procedure for decommissioning a tower crane. It ensures that the sequence follows manufacturer guidelines to maintain structural balance and worker safety. 1. Preliminary Preparations Before any physical work begins, the following site preparations are mandatory: Site Inspection: Conduct a walkthrough to identify hazards and ensure the ground is stable for the auxiliary mobile crane Weather Monitoring: Check the forecast; work must stop if wind speeds exceed manufacturer limits (typically Exclusion Zones: Barricade the entire dismantling radius to prevent unauthorized access. Equipment Check: Verify that all lifting gear (slings, shackles, pins) has valid Third Party Inspection certificates. 2. Dismantling Sequence The dismantling process generally follows the reverse order of assembly to maintain the center of gravity: Method Statement Dismantle Tower Crane - Scribd
Tower Crane Dismantling Method Statement 1. Project details
Project: Tower crane dismantling at [Project name / address] Client: [Client name] Contractor: [Contractor name] Crane make/model/ID: [e.g., Liebherr 175 EC-B], SWL: [tonnes] Dismantling date(s): [start — finish] Prepared by: [Name], Date: April 10, 2026 Revision: 0
2. Scope of works
Safe planning, rigging, step-by-step dismantling, transportation and storage of the tower crane and associated components; removal of foundations/bolts if requested; reinstatement of area.
3. References and standards
Manufacturer’s dismantling manual and instructions Local health & safety regulations and construction codes Relevant standards (e.g., ISO 9001 / ISO 14001 as applicable, EN 14439, local crane regulations) Site-specific safety plan and permit to work procedures tower crane dismantling method statement
4. Responsibilities
Site Manager: overall coordination, permits, client liaison. Crane Dismantling Supervisor (appointed): confirm method, sequence, safe system of work. Appointed Crane Operator(s): operate mobile cranes/derrick per plan. Riggers/Slingsmen: attach/detach loads, conduct taglines. Banksman/Signalperson: maintain exclusion zone and signalling. Safety Officer: monitor controls, toolbox talks, PPE compliance. Lifting Equipment Inspector: pre-use inspection and certificates.
5. Permits and notifications
Obtain permit to work, lifting permit, hot works permit (if needed), confined space permit (if needed). Notify local authorities/traffic management if road closures or oversized loads are required. Notify personnel, site neighbours and stakeholders of planned activities and exclusion zones.
6. Risk assessment / hazards Key hazards and controls: